Short answer
Not automatically in full. On the breaching party's request, a court can reduce liquidated damages that are 'excessively higher' than the actual loss, and as a general rule more than 30% above that loss counts as excessive (Civil Code art 585; Supreme People's Court Contract Interpretation 2023, art 65). The 30% is measured against your loss, not the contract price. A clause saying the figure cannot be adjusted has no effect (art 64).
Liquidated damages work in China, and courts are generally more willing to award an agreed sum than to grant an injunction. The risk is a figure that cannot be justified.
How a court assesses the figure
- The starting point is the loss caused by the breach, including the profit you would have earned, limited to what the breaching party foresaw or should have foreseen when contracting (Civil Code art 584).
- The court also weighs the parties' status, the type of transaction, how far the contract was performed, fault, and the background.
- The breaching party must prove the figure is excessive, but you should still produce evidence that it is reasonable.
- A party in bad-faith breach will generally not get a reduction.
- If the agreed sum is lower than the loss, the court can increase it on request.
Interaction with deposits
Where the contract has both a deposit (定金, dingjin) and liquidated damages, the innocent party must choose one, and can claim any loss the deposit does not cover (art 588).
Drafting points
- Tie the figure to a documented estimate of loss: margins, tooling, lost orders.
- Add that the breaching party pays reasonable lawyers' fees, preservation and translation costs.
Our contract drafting and review service and NNN agreement service set the figure; see an NNN with a Shenzhen manufacturer. Send us the clause for a view.
How ANHE helps
We work out a damages figure you can justify with evidence, and have a licensed PRC law firm write it into the Chinese text of the contract or NNN. If a claim arises, ANHE manages the evidence of loss and the case through PRC counsel to completion.
Sources
- Civil Code of the PRC
- SPC Interpretation on the General Provisions of the Contract Part of the Civil Code (2023)
Last reviewed 19 November 2026. General information, not legal advice: Chinese law and practice change, and what is possible depends on the facts.
